1642 K Street NE Washington, DC
Project Status: UNDER CONSTRUCTION
Project Type: 12 Condos
Project Summary: Flooring installations are 80% complete and plumbing installations are 70% complete as of November 08, 2024. We will soon start on outside landscaping and finishes.
Two Week Look Ahead: We will finish the top 6 units to be able to list on the market in January 2025.
Current - Completion Stage











Siding Painting - COMPLETE
Tile and Cabinet Installation - COMPLETE

























COMPLETE - Drywall Installation




















COMPLETE - Building Inspection



























COMPLETE - Building Inspection




















COMPLETE - MEPs




















COMPLETE - Framing













































COMPLETE - Ground Plumbing







COMPLETE - Sheeting & Shoring


























COMPLETE - Demolition